Back

Knitting-I (AC) 2022

2022BUTEX-AC

Knitting-I exam (FE 307) from the 2022 Level-3 Term-I finals, BUTEX affiliated colleges. Covers weft knitting machine features, latch needle construction, knit cam functions, timing concepts, V-bed machines, and fabric production calculations per shift.

BANGLADESH UNIVERSITY OF TEXTILES

B. Sc. in Textile Engineering (For Affiliated Colleges)

Level-3 Term-I, Final Exám-2022
Subject:
Knitting-I (Code: FE 307)
Time: 3.0 Hrs. Full Marks: 72
(Use separate answer script for Part: A and Part: B)

(All parts of a question must be answered consecutively)


Part: A
(Answer any three questions)

1. ⁢(a) State the features of weft knitting machine.

(b) Describe the construction of Latch Needle with suitable sketch.

(c) Calculate the length of fabric produced per 8 hour shift at 85% efficiency of a knitting machine from the following particulars:

No of Feeders 40

Fabric open width 260 cm

Stitch density 15

Machine Speed 24 rpm

Machine diameter 30 cm

Sign in to see the full question paper