Back

FM-I (AC) 2024

2024BUTEX-AC

Fabric Manufacturing-I paper (YE 201) from BUTEX affiliated colleges' 2024 Level-2 Term-I finals. Covers winding faults and machine diagrams with time calculations, slasher sizing units, creel types, sectional warping, and drafting with reed count conversions.

BANGLADESH UNIVERSITY OF TEXTILES

B. Sc. in Textile Engineering ㅤ(For Affiliated Colleges)

Level-2 Term-I, Final Exám-2024
Subject:
Fabric Manufacturing-I (Code: YE 201)
Time: 3.0 Hrs. Full Marks: 72
(Use separate answer script for Part: A and Part: B)

(All parts of a question must be answered consecutively)


Part: A
(Answer any three questions)

1. ⁢(a) Define fabric. Differentiate between woven and knit fabric.

(b) Which types of faults are removed during yarn preparation? Write down the characteristics of non-precision winding.

(c) Describe the cone winding machine with sketch.

(d) The actual production/drum/minute of a cone winding machine is 750 m. Calculate the time required for winding 1500 lbs of 25s cotton yarn on 20 drums.

[3+3+3+3 = 12]

2. (a) Define loom. Write down the main feature of pit loom and chatranojon loom.

(b) Describe the various units of a slasher sizing process with sketch.

(c) Calculate the production in kg per shift of 8 hours of a high speed loom considering the following parameters: RPM 1200, Diameter of winding drum 4.5”, No. of drums 90, yarn count 32 tex Efficiency 82%.

[4+4+4 = 12]