Apparel Production, Planning & Control exam (AE 405) from the 2023 Level-4 Term-I finals, BUTEX affiliated colleges. Includes PPC function comparisons, capacity definitions, SAM-based production calculations, UPS versus PBS systems, and cutting room management.

BANGLADESH UNIVERSITY OF TEXTILES

B. Sc. in Textile Engineering (For Affiliated Colleges)

Level-4 Term-I, Final Exám-2023
Subject:
Apparel Production, Planning & Control (Code: AE 405)
Time: 3.0 Hrs. Full Marks: 72
(Use separate answer script for Part: A and Part: B)

(All parts of a question must be answered consecutively)


Part: A
(Answer any three questions)

1. ⁢(a) Define production planning and production Control.

(b) Describe the functions of production planning and control.

(c) Make a list of comparison between production planning and control.

(d) Write short note on Capacity planning and Line planning.

[3+3+3+3=12]

2. (a) Mention the steps in process planning.

(b) Define i) Design Capacity ii) System Capacity iii) Installed Capacity iv) Rated Capacity.

(c) Suppose a factory has 8 sewing lines and each line has 25 machines. Total 200 machines and the working shift is 10 hours per day. Total factory capacity per day is 2000 hours (200 machines × 10 hours). If factory is producing only one style of SAM 25 minutes and used all 200 machines daily production capacity at 50%. Calculate production capacity in pieces.

(d) A garment has 20 operators who work 8 hours a day. The plant has 90% efficiency level. Working shift is 8 hours a day in which 1 hour is mainly for lunch and tea time break. Find out potential capacity for next 10 days.