Level-3 Term-I 2019 exam on Apparel Manufacturing-II (AE 309) from BUTEX affiliated colleges, 72 marks. Candidates answered on modular production, line balancing for polo shirts, stone enzyme washing, sand blasting, ozone and laser fading, and apparel dyeing.
Level-3 Term-I, Final Exám-2019
Subject: Apparel Manufacturing-II (Code: AE 309)
Time: 3.0 Hrs. Full Marks: 72
(Use separate answer script for Part: A and Part: B)
(All parts of a question must be answered consecutively)
Part: A
(Answer any three questions)
1. (a) What is apparel production system?
(b) Describe the 'Modular Production System' process.
(c) Make differentiate between UPS and PBS.
(a) State the necessity of inventory control in Apparel industry.
[2+4+3+3=12]
2. (a) Define layout planning and line balancing.
(b) Why layout planning is essential in Apparel industry? Explain briefly.
(c) Describe the advantages of proper line-balancing.
(d) Write down the line-balancing system for making polo-shirt.
[2+3+3+4=12]
3. (a) Write down the objectives of stone enzyme washing.
(b) Describe the procedure of stone enzyme washing process to wash 70kg denim garments with a suitable recipe. i