Time: 3.0 Hrs. Full Marks: 105
(Use separate answer script for Part: A and Part: B)

(All parts of a question must be answered consecutively)


Part: A
(Answer any three questions)

1. ⁢(a) Whatis production and productivity? Explain the causes of low productivity?

(b) State the differentiate between progressive Bundle system (PBS) and unit production system (UPS).

(c) Discuss about Modular Manufacturing system.

[6.5+S+6=17.5]

2. (a) Discuss the benefits of inventory control.

(b) Describe the responsibilities of finishing manager in a garments industry.

(c) Mention the scope of product development in the apparel industry.

(d) What are the steps that taken to control quality in finishing section.

[3.5+5+5+4=17.5]

3. (a) What is cutting room management? Explain the production process of cutting room.

(b) What is line balancing? State the steps of line balancing and importance of line balancing.

(c) What is color staining? Explain the causes and remedies of color staining.