2016 Level-3 Term-II question paper on Apparel Manufacturing-II (AME 353) from BUTEX affiliated colleges. Examines line balancing objectives, cutting efficiency improvement, material management, economic order quantity problems, and enzyme washing of denim garments.
Level-3 Term-II, Final Exám-2016
Subject: Apparel Manufacturing-II (code AME 353)
Time: 3.0 Hrs. Full Marks: 105
(Use separate answer script for Part: A and Part: B)
(All parts of a question must be answered consecutively)
Part: A
(Answer any three questions)
1. (a) Define "Line Balancing"& "Lay Out Planning" .
(b) Write down the objectives of line balancing.
(c) Prepare a suitable machine sequence to produce a t-shirt. ;
(d) What factors should be checked in marker making, inspection before cutting?
[4+3+7+3.5=17.5]
2. (a) Which points are to be considered before spreading & marker making ? .
(b) If you get charge of cutting section, how will you improve the cutting efficiency?
(c) Which activities are involved in materials management? Discuss.
[6+5+6.5=17.5]
3. (a) Write down the objectives and activities involved in "Material Management System".
(b) State the functions and importance of purchasing department.